Airports become grid customers

19 November 20263 min read

On 14 November 2026, China’s CE-25A completed its first piloted flight over Binzhou, in Shandong Province. It is a 10-tonne electric commercial aircraft, built by the Commercial Aircraft Corporation of China (COMAC) and designed for up to 19 passengers and a 400 km range. Two pilots and one flight-test engineer were on board (Electrek, ECNS).

The aircraft is the headline. For power engineers, the story is on the ground.

Airports become grid customers

Fast turnarounds at the airports will require megawatt-scale chargers. That brings substation upgrades, tariff and demand planning, possibly on-site storage, and power-quality work.

Fast turnaroundAn aircraft that sits on the ground earns nothing
↓
Megawatt-scale chargersPower = energy ÷ time
↓ lands on the grid as four jobs
Substation upgradesTransformer, switchgear and protection at the connection point
Tariff and demand planningPeak demand, not just energy, sets the bill
On-site storagePossibly: charge slowly, discharge fast
Power-quality workHarmonics, dips and flicker from fast charging
Each box is a project an airport, a utility or a consulting engineer will have to scope.

The four jobs

Substation upgrades. A bank of aircraft chargers is a new, concentrated load. The connection point needs enough transformer capacity, switchgear and protection for it. At the scale of tens of megawatts this is a substation project, not a socket.

Tariff and demand planning. Many large customers are billed for their peak demand as well as the energy they use. Several aircraft charging at the same moment sets that peak. Staggering charging, or planning the flight schedule around the demand limit, can matter as much as the hardware.

Possibly on-site storage. A battery at the airport can charge slowly from a modest connection between flights and then discharge fast into the aircraft. That trades the cost of a bigger grid connection against the cost of the battery. Which side wins depends on the site, which is why the word is “possibly”.

Power-quality work. Fast chargers are power electronics. They inject harmonic currents, and sudden load steps cause voltage dips and flicker, most of all at a weak supply point. The usual references are the South African voltage-quality standard NRS 048-2 and IEEE 519 for harmonics.

Why megawatts: the arithmetic

The battery capacity of the CE-25A has not been published, so these numbers are illustrative assumptions, not aircraft data. The relationship is simple. To refill a pack of energy E in a turnaround time t, with charging efficiency η:

P = E ÷ (η × t)

Taking η = 0.9:

Pack energy Turnaround Charging power
1 MWh 30 minutes about 2.2 MW
2 MWh 30 minutes about 4.4 MW
2 MWh 20 minutes about 6.7 MW

Now put four aircraft on the apron at once, each taking 4.4 MW. That is about 18 MW of new load at one site, which is the substation-scale problem described above.

What it means

This speaks to the topic we discussed yesterday in ELP, regarding AI.

As technology becomes a commodity, new technology frontiers are opened.

The electric aircraft is one technology maturing. The frontier it opens is on the ground: megawatts, substations, tariffs and power quality at the airport.