19 November 20262 min read

Verify the design. Validate the product.

That is the V-Model, and it’s as basic to engineering as PMBOK is to project management.

↓ Verify the design“Are we building it right?”
↑ Validate the product“Did we build the right thing?”
URSUser Requirement Specification
PQPerformance Qualification
Functional SpecFunctional Requirement Specification
OQOperational Qualification
Technical SpecTechnical Requirement Specification
IQInstallation Qualification
ConstructionFactory Acceptance Test (FAT) and Site Acceptance Test (SAT)
Down the left leg the design is checked level by level. Up the right leg the finished product is tested back to the need. The dashed lines pair each specification with its qualification.

Down the left leg: verify the design

Go from the user’s need to the build: URS → Functional Spec → Technical Spec → Construction. Check each level against the one above it.

Verification is a design function: “are we building it right?”

Up the right leg: validate the product

Test from the build back up to the need: FAT/SAT → IQ → OQ → PQ.

Validation asks: “did we build the right thing?”

The horizontal lines tie the two together

Every spec has a matching qualification:

  • Technical Spec ↔ Installation Qualification
  • Functional Spec ↔ Operational Qualification
  • URS ↔ Performance Qualification

Write the test protocol and its acceptance criteria at the same time as the specification. If you can’t say how a requirement will be validated, it isn’t a requirement yet.

Where the V comes from

The V-Model is the signature tool of systems engineering. INCOSE (International Council on Systems Engineering) describes it as “the” icon of the discipline. If PMBOK is the body of knowledge for project managers, the INCOSE Systems Engineering Handbook is the equivalent for systems engineers.

Systems engineering looks at the whole system across its full life cycle: needs → requirements → design → build → verification → validation → operation → disposal. The V is just that life cycle folded in half, so that every requirement faces its test.

There’s an INCOSE South Africa chapter for anyone who wants to go deeper.